Home > news > Cone crusher main working parts

Cone crusher main working parts

Cone crusher main working parts and components replacement method, separately carries on the detailed introduction of the following

1 Cone crusher ore must be assigned work in the intermediate plate, in order to prevent crushing machine overload, making the lining uneven wear; do not allow direct the ore into the crushing cavity. The right to mine: ore distribution plate is uniformly dispersed in the crushing cavity, into the ore can not be higher than the rolling mortar wall level.

2 Crusher machine do not load to start, to avoid accidents crusher ore size≤ 85% largest feed port size, otherwise it will lead to the crusher yield reduction, cone crusher in some parts to be damaged.

3 When parking, you must first stop the feeder, and made into the crushing chamber of ore crushing after discharge, the crusher parking.

4 Crusher machine work to always check the locking system pressure and hydraulic station work, found problems in time, rolling mortar wall replacement, rolling mortar wall U screw breaking machine manufacturers nail in the adjustment ring, between injection of zinc alloy, which closely, new installations or replacement of the rolling mortar wall, in 6 - 8 hours, should be examined for fastening, again and tighten U screw.

5 Gear, the round plate wear due to friction between gears, effect of cement production technology gap changes, in order to ensure the normal meshing gear must be on the bottom cover gasket gasket is added, the thickness should be equal to the amount of wear plate.

6 Bearing and sealing device, mounting bearing, careful not to wire rope broken oil retaining ring ( hardwood such as support in between the wire rope ). When assembling, bearing spherical should be scraping, ensure the cone crusher and the bowl-shaped cross spherical outer circular contact ring should ensure that the 0.35 0.5mm annular clearance. The bowl-shaped bushing is used around the perfusion of the Ba alloy lock pin fixed on the bearing frame, prevent the bowl-shaped bushing along the circumferential side where rotation. Bearing frame and the frame body by keys ( PIN ) is fixed, if found in the bearing frame and the frame body has a gap must be deal with immediately.